Sample plan

The Homestead Plan · Sample no. 01

Five acres of raw land, drawn into a homestead.

A site plan you can walk, a build order you can follow, and a list of everything it takes, from the first load of gravel to the root cellar.

The land
5.00 acres, 440 x 495 ft, mostly open, timber along the north
The lay
Gentle south-facing slope, seasonal creek on the east, county gravel road on the south
The family
Four people, building it themselves in stages
Starting point
No power at the lot line, no well, no septic, no driveway

This is a sample. The property is made up to show the product: there is no such address, owner or parcel. The setting is the Flathead Valley of northwest Montana, and every rule, date and cost range on this page is real and cited.

See the site planOpen the PDFGet a plan for your land

The brief

What this family asked for

A home they can heat with their own wood. Water from their own well. A garden big enough to matter, fruit trees, a dozen hens, and room for a few animals later. Power that does not depend on a line that is not there.

Their starting budget, in words. The land is paid for. They have enough set aside to pay for the well, the septic system and the driveway outright in the first two seasons. Everything after that gets built from income, in stages, with their own hands doing most of the work. That one fact shapes the whole plan: the costly, hired, permitted work comes first, and the work a family can do comes after.

Sheet S-1 · The site plan

Everything on the land, to scale

North is up. Every building, fence and trench is drawn at its real size and in its real place. The numbers match the key.

Sheet S-1, site plan of the sample five acre homesteadPlan view, north up. County gravel road on the south line, seasonal creek inside the east line, existing timber across the north. The driveway enters from the road and climbs to a parking court beside the house at the middle of the lot. The well sits uphill of the house; the septic tank, drainfield and replacement area sit downhill. Pasture paddocks and the barn run along the west side; kitchen garden, hen run and orchard lie east of the house; a future expansion zone lies along the road.+2+4+6+8+10+12+14+16+18FEETABOVEROAD440 FT495 FT143 FT92 FTEXISTING TIMBER · WOODLOT21PASTUREPADDOCK D11PADDOCK CPADDOCK BPADDOCK A12BARN + SHOPWINTER YARD1HOUSE2WELL34DRAINFIELD5REPLACEMENTAREA, KEEP CLEAR6716KITCHEN GARDEN8ORCHARD910HEN RUN13141517100 FT FIRE RINGWELL ISOLATION ZONE, 100 FTFUTURE EXPANSIONFIFTH PADDOCK, HAY OR A CABIN18192022CREEK SETBACK, 100 FTSEASONAL CREEK23COUNTY GRAVEL ROADEXISTING CULVERTN02550100FEETSCALEGRID 50 FT · CONTOURS 2 FTSAMPLE PROPERTY, NOT A SURVEY
S-1 Site planScale bar on the drawing · Grid 50 ft · Contours 2 ft Sample property5.00 acres, northwest Montana Planning drawingNot for construction Ready or Not Co.

Open the drawing full size

Key to the plan

  1. 1House 28 x 44 ft, long side to the south, 8 x 32 ft porch
  2. 2Well Uphill of everything that drains, 147 ft from the drainfield
  3. 3Septic tank 27 ft below the house, gravity fed
  4. 4Drainfield 90 x 50 ft, drawn as four 90 ft laterals along the contour
  5. 5Replacement area A second 90 x 50 ft kept clear for the day the first field retires
  6. 6Solar array 16 panels on a 30 ft ground mount, open sky to the south
  7. 7Power shed 8 x 10 ft for batteries, inverter and a generator pad
  8. 8Kitchen garden 70 x 80 ft inside an 8 ft deer fence, drawn on S-4
  9. 9Orchard 12 trees at 24 ft, fenced 72 x 96 ft
  10. 10Coop and hen run 8 x 12 ft coop, 36 x 42 ft run
  11. 11Pasture 0.76 acre in four rotation paddocks, A to D
  12. 12Barn and shop 30 x 40 ft with a fenced winter yard
  13. 13Root cellar 12 x 16 ft, bermed into the slope
  14. 14Woodshed 8 x 16 ft, 36 ft from the house wall
  15. 15Rain tanks Two at the house, one at the barn
  16. 16Compost Three 4 ft bins at the garden corner
  17. 17Fire-safe clearing Rings at 5, 30 and 100 ft from the house
  18. 18Future expansion 160 x 102 ft held open along the road
  19. 19Driveway 12 ft wide, 298 ft from the road to the court
  20. 20Parking court 44 x 46 ft, room to turn a truck and trailer
  21. 21Existing timber Woodlot and shelter; thinned inside the 100 ft ring
  22. 22Gate and culvert At the county road approach
  23. 23Seasonal creek 100 ft setback line drawn for anything septic

Lines

  • Property line
  • Contour, 2 ft
  • Woven wire fence
  • Deer fence
  • Water line
  • Sewer line
  • Power in trench
  • Creek setback, 100 ft
  • Well isolation zone
  • Fire-safe rings
  • Kept clear or below ground
  • Future ground

Why it sits where it sits

Six decisions that make the rest easy

1

Water uphill, waste downhill

The well sits at the top of the open ground. The septic tank, the drainfield and its replacement area sit below the house, where gravity takes everything away from the water you drink. The well stands 147 ft from the drainfield, and the ground between them rises about 6 ft.

2 The house takes the middle of the slope

High enough to drain, low enough to stay out of the timber. Its long side faces south for winter sun, and it sits 300 ft back from the road.

3 The creek is left alone

Nothing septic comes within 133 ft of the bank. The orchard and a grass strip fill that ground, and the hens stay 55 ft back.

4 Daily chores stay close

The kitchen garden gate is 26 ft from the kitchen door and the hens are 109 ft. The barn is 120 ft, close enough in January and far enough in July.

5 Animals stay off the well

The winter yard, the hen run and the compost all sit more than 100 ft from the well, outside the ring drawn around it.

6 Room is left on purpose

The replacement drainfield and the ground along the road stay open. A plan that fills every corner on day one has nowhere to grow.

Distances checked against the county table

Measured on S-1, set beside the minimums in the Flathead County onsite wastewater regulations.1

BetweenOn this planCounty minimum
Well to drainfield147 ft100 ft
Well to septic tank119 ft50 ft
Drainfield to creek bank133 ft100 ft
Replacement area to creek bank143 ft100 ft
Septic tank to creek bank186 ft50 ft
Drainfield to property line130 ft10 ft
Drainfield to house foundation55 ft10 ft
Septic tank to house foundation27 ft10 ft
Septic tank to drainfield23 ft10 ft

Distances we chose

No rule sets these. They are our own planning choices, measured the same way.

BetweenOn this planWhy
Well to the north property line103 ftThe whole 100 ft isolation ring stays on your own ground
Well to hen run127 ftManure stays outside the ring
Well to winter yard105 ftSame reason
Well to compost105 ftSame reason
Hen run to creek bank55 ftA grass strip between hens and water
House to the timber edge92 ftInside the 100 ft ring, so that edge gets thinned
Woodshed to house36 ftFirewood sits outside the 30 ft ring

Sheets S-2 to S-4

Three more drawings, same hand

Sheet S-2, zone diagramThe same five acres sorted by how often the family walks to each place, drawn over the grid, contours, fences and buildings of the site plan, with the walking distance from the kitchen door marked at each place. Zone 1 wraps the house, porch, kitchen garden and woodshed. Zone 2 holds the hens, compost, root cellar, power shed and well. Zone 3 is the orchard, barn and nearest paddock. Zone 4 is the outer paddocks, the woodlot and the future ground. Zone 5, the creek corridor and the septic ground, is left alone.+2+4+6+8+10+12+14+16+18FEETABOVEROADWELL64 FTWOODSHED 43 FTROOT CELLAR28 FTCOMPOST95 FTHENS109 FTPOWER SHED52 FTORCHARD 90 FTBARN 120 FTKITCHEN GARDENGATE 26 FTHOUSESEPTIC GROUNDKEEP CLEARPADDOCKSFUTURE GROUNDWOODLOTSEASONAL CREEKCOUNTY GRAVEL ROAD12334445502550100FEETSCALEGRID 50 FT · CONTOURS 2 FTDISTANCES ARE WALKS FROM THE KITCHEN DOORN1MANY TIMESA DAY2EVERYDAY3A FEW TIMESA WEEK4WEEKLY ORBY SEASON5LEFTALONE
S-2 ZonesHow often you walk there Sample property5.00 acres, northwest Montana Planning drawingNot for construction Ready or Not Co.

Open the drawing full size

Near things near, far things far

Sort the land by how often your boots go there, and put the daily places within a short walk of the kitchen door. The dotted lines are the paths you will wear into the grass.

  1. 1Many times a day. House, porch, kitchen garden (26 ft from the kitchen door), rain tanks, woodshed (43 ft), parking court.
  2. 2Every day. Hens (109 ft), compost (95 ft), root cellar (28 ft), power shed (52 ft), well (64 ft).
  3. 3A few times a week. Orchard (90 ft), barn and winter yard (120 ft), the nearest paddock.
  4. 4Weekly or by season. Outer paddocks (the far corner is 323 ft away), the woodlot, the future ground.
  5. 5Left alone. The creek corridor (181 ft east of the house) and the septic ground. Mow it, walk it, build nothing on it.
Sheet S-3, sun and wind at the house siteSun path diagram for latitude 48.2 degrees north. On June 21 the sun rises at a bearing of 53 degrees and stands 65 degrees high at noon. On December 21 it rises at 127 degrees and reaches only 18 degrees at noon. The house sits with its long glazed side to the south. Prevailing wind is from the south to south-southeast. A section shows a 2.5 foot eave shading the south glass in June and admitting the December sun.30°60°NESW53°307°127°233°JUNE 21 NOON, 65° HIGHEQUINOX NOON, 42°DEC 21 NOON, 18°GLASS FACES SOUTHWINTER NOON SHADOWPREVAILING WINDS TO SSE, ALL YEARTIMBERJUNE NOON 65°DEC NOON 18°SUN REACHES 21 FT IN2.5 FT EAVESOUTHGLASSSECTION AT THE SOUTH WALLWHAT THE EAVE DOESHIGH SUMMER SUN STOPS AT THE EAVEAND MOST OF THE GLASS STAYS IN SHADE.LOW WINTER SUN PASSES UNDER ITAND WARMS THE FLOOR.
S-3 Sun and windAt the house site, latitude 48.2 north Sample property5.00 acres, northwest Montana Planning drawingNot for construction Ready or Not Co.

Open the drawing full size

Build for the low winter sun

On June 21 the sun rises at a bearing of 53 degrees, far to the northeast, and stands 65 degrees high at noon. On December 21 it rises at 127 degrees and climbs to only 18. Daylight runs about 16 hours at midsummer and a little over 8 at midwinter.

So the house turns its long glazed side south. A 2.5 ft eave shades most of that glass in June and lets the December sun reach about 21 ft across the floor. At noon in December a shadow is 3.0 times as long as the thing that casts it, which is why the solar array has open ground to its south and the timber stays to the north.

The prevailing wind at the Kalispell airport comes from the south to south-southeast in every month of the year.31 Wind is local, so watch one winter of drifts before you plant a shelterbelt.

Sheet S-4, kitchen garden layoutThe 70 by 80 foot kitchen garden inside an 8 foot deer fence. A 12 by 24 foot hoop house and two raspberry rows sit along the north side. Twelve raised beds, each 4 by 12 feet with 3 foot paths, fill the middle beside a perennial bed of asparagus and rhubarb. A 58 by 21 foot row block for potatoes, winter squash, sweet corn and dry beans runs along the south. Gates open west to the house and south for a cart.HOOP HOUSE 12 × 24TOMATOES, PEPPERS,EARLY AND LATE GREENSRASPBERRIES, TWO 26 FT ROWS172839410511612ASPARAGUS+ RHUBARBPERENNIALBED11 × 28POTATOESPOTATOESPOTATOESDRY BEANSWINTER SQUASHSWEET CORN, SHORT SEASONROW BLOCK 58 × 21, IN THE GROUNDHYDRANTWASH70 FT80 FT43124GATETOHOUSE10 FT GATEN
S-4 Kitchen garden70 x 80 ft inside an 8 ft deer fence Sample property5.00 acres, northwest Montana Planning drawingNot for construction Ready or Not Co.

Open the drawing full size

A garden sized for four people and a short season

Twelve raised beds of 4 x 12 ft carry the daily vegetables. A 58 x 21 ft row block carries the storage crops: potatoes, dry beans, winter squash and a short-season sweet corn, with the corn on the north so it shades nothing.

The 12 x 24 ft hoop house stretches the season at both ends, which is what tomatoes and peppers need here. The asparagus and rhubarb bed and the two raspberry rows are planted once and picked for years.

Beds are 4 ft wide so you can reach the middle from either side, and paths are 3 ft so a cart fits. The 10 ft gate on the south takes a load of compost.

What goes in the twelve beds

  1. 1Peas, then fall greens
  2. 2Carrots and beets
  3. 3Onions
  4. 4Cabbage, broccoli, kale
  5. 5Lettuce and spinach, sown in turns
  6. 6Bush beans
  7. 7Summer squash
  8. 8Garlic, planted in fall
  9. 9Chard and kale
  10. 10Strawberries
  11. 11Cucumbers on a trellis
  12. 12Herbs and flowers

Reading the land

What to look at before you buy or build

Ten things to settle while the land is still someone else’s problem.

  1. Water first

    Ask what the neighbors drilled. The Montana Bureau of Mines and Geology keeps well logs by location, and in the Flathead Valley it describes a deep aquifer whose top lies “75 to over 400 feet below the land surface.”32 Depth is the biggest swing in a well bill, so look before you offer.

  2. Where the septic can go

    Find out whether the lot carries a Certificate of Subdivision Approval. In Flathead County you start with a Land Research Request, and the Health Department tells you whether the lot needs a site review or a full site evaluation.2 1 A lot that cannot take a drainfield is a lot you cannot live on.

  3. Groundwater in spring

    Walk it in April and May, not only in August. Where groundwater may sit within 7 feet of the surface the county requires monitoring holes,1 and its monitoring season runs from January into June.5 Miss the season and you wait a year.

  4. Legal access

    Read the deed and the plat for recorded access. A two-track that everyone uses is not the same as a right to use it. Ask the title company to show you the easement.

  5. The slope and the sun

    A gentle slope that faces south is the best ground in a cold valley: it warms early, drains cold air and gives the house winter sun. At this latitude the December noon sun stands only 18 degrees above the horizon, so anything tall to the south costs you light.

  6. The creek

    A seasonal creek is a gift and a set of limits. The county measures septic setbacks from “any natural or man-made body of water or watercourse,” and nothing in that definition is limited to year-round water.1 Ask whether any of the lot is mapped floodplain.

  7. Power

    Ask the electric cooperative for a work order before you assume either answer. Flathead Electric says plainly that it does not give out ballpark or per-foot estimates,36 so the only real number is the one on your own estimate.

  8. Zoning and covenants

    Flathead County has zoned and unzoned ground. Call Planning and Zoning with the legal description and ask which you are in, then read any covenants recorded on the lot. The county’s standard zoning districts carry a 20 foot structure setback from streams.21

  9. Fire

    Look at what burns between you and the nearest road out. One way in is one way out. Note where a fire engine could turn around.

  10. The neighbors

    Knock on two doors. Ask about the well, the wind, the snow, the bears and the road in March. You will learn more in twenty minutes than in a week of maps.

The build, from raw land

Five phases, in the order that saves money

Each phase says what gets built, in what order and why, what to hire, what a family can do, and what needs a permit.

1

Phase 1 · First dry season

Access, water and a place to stay

Nothing else can start until a truck can get in and water comes out of the ground. The well also tells you the truth about the land before you spend on a house.

  1. Paperwork before dirt. File the Land Research Request with the Health Department, the approach permit with Road and Bridge,16 the address request with county GIS17 and the Notice of Intent for the well with DNRC.8 Call 811 before any digging; utilities have 2 business days to mark.29
  2. Approach, culvert and driveway. Build the 298 ft driveway and the 44 x 46 ft court first. Every later delivery rides on it: the drill rig, the septic tank, the concrete.
  3. The well. Drill at the mark on S-1, uphill of the house and 147 ft from the drainfield site. Set the pump, the pressure tank and one frost-free hydrant at the court.
  4. A place to stay. Park a trailer or raise a small dry cabin on the court. Living on the land for one full winter teaches you where the snow drifts and where the sun lands before you pour a foundation.
  5. Thin the timber edge. Start the 100 ft ring now. The thinnings become next year’s firewood.

Hire out

  • Well drilling (a licensed water well contractor)
  • Driveway base and culvert, unless you own the equipment
  • Any survey needed to find the corners

Do it yourselves

  • Clearing and brushing the driveway line
  • Thinning and limbing inside the 100 ft ring
  • Setting the gate
  • Trenching the first water line, if the driller agrees

Permits and filings

  • County roadway permit for the approach16
  • DNRC Notice of Intent (Form 602I) before the well is put to use, then a Notice of Completion (Form 602)8 10
  • Address from county GIS17
2

Phase 2 · Second building season

Septic, power and the house shell

These three depend on each other. The septic permit fixes where the house can sit, the house fixes where power lands, and none of it can be undone cheaply later.

  1. Septic permit and install. The Health Department permits the system before any of it is built.1 On S-1 the tank sits 27 ft below the house and the field is drawn as four 90 ft laterals along the contour. That drawing is a placeholder: the designer sizes the real field from your soil.
  2. Stake the replacement area. The county requires room for “a 100% replacement of the original system.”1 Fence nothing, plant no trees and park nothing on that second 90 x 50 ft.
  3. Power. Mount 16 panels on the 30 ft ground rack, set the power shed beside it and trench 36 ft to the house. Sixteen 400 watt panels make a 6.4 kilowatt array; your installer sizes the batteries from your real loads.
  4. The house shell. Foundation, frame, roof, windows and doors for a 28 x 44 ft house. Get it weathertight before the snow and finish the inside over winter.

Hire out

  • Septic design and install, unless you take the county self-installer license
  • Foundation and concrete
  • Battery, inverter and service wiring, or have your own work inspected
  • Roofing, if heights are not your trade

Do it yourselves

  • Framing, with a few experienced friends
  • Ground mount racking
  • Trenching for power and sewer
  • Insulation, siding, interior finish
  • Your own plumbing, which Montana allows a homeowner on a home for personal use

Permits and filings

  • Septic permit from the Flathead City-County Health Department; it lapses if the system is not installed and approved within 24 months1
  • State electrical permit for all wiring, with a homeowner permit option14
  • No county building permit: “Flathead County does not have a building department.”12 Private homes of four units or fewer are exempt from the state building permit13
  • A plumbing permit is not needed when a homeowner does the plumbing on a home for personal use15
3

Phase 3 · Starts the first spring

Food: garden, orchard and hens

Fruit trees take years, so they go in the ground long before the house is finished. The garden and hens follow as soon as someone is on the land every day.

  1. Orchard first. Fence 72 x 96 ft and plant 12 trees at 24 ft. Fence before you plant; deer find a new tree in a night.
  2. Kitchen garden. Fence 70 x 80 ft, set the gates, then build 12 raised beds of 4 x 12 ft and break the 58 x 21 ft row block (sheet S-4).
  3. Hoop house. A 12 x 24 ft tunnel buys tomatoes and peppers extra weeks at both ends of a season whose median length between frosts is about 100 days.
  4. Hens. Coop first, then the 36 x 42 ft run, then the birds. In bear country Montana FWP says to “secure vulnerable livestock (chickens, goats, sheep) with an electric fence.”28
  5. Compost and water. Three bins at the garden corner and a hydrant on a 128 ft line from the well.

Hire out

  • Nothing here has to be hired

Do it yourselves

  • All of it. This is the phase a family builds together
  • Ask FWP about electric fence design; they offer help

Permits and filings

  • None for a garden, an orchard or a coop in the unzoned county. If the lot is zoned, ask Planning and Zoning about animals and setbacks
4

Phase 4 · Once the house is lived in

Animals, storage and the root cellar

Animals need you home twice a day, every day. They come after the house is lived in, the fences are tight and there is a dry place for hay.

  1. Fence the pasture. 820 ft around the outside, 330 ft of cross fence to make four paddocks and 218 ft for the winter yard. Montana defines a legal fence as “at least 42 inches but not more than 48 inches in height.”27
  2. Barn and shop. A 30 x 40 ft pole building at the head of the paddocks, on a 71 ft gravel spur from the court.
  3. Water and power to the barn. 145 ft of water line with a hydrant at the court and one at the barn, and 122 ft of power trench.
  4. Root cellar. Dig 12 x 16 ft into the slope behind the house while the excavator is on site for the barn.
  5. Woodshed. 8 x 16 ft at the north edge of the court, 36 ft from the house wall.
  6. Then the animals. Start small: a few goats or hair sheep moved through paddocks A to D. Ask MSU Extension in Flathead County for a stocking rate for your grass before you buy.

Hire out

  • Pole building shell, or the post setting at least
  • Excavation for the root cellar
  • Barn subpanel wiring, or have your own work inspected

Do it yourselves

  • All fencing
  • Root cellar walls, roof and shelving
  • Woodshed
  • Stalls, hay storage and gates

Permits and filings

  • State electrical permit for the barn wiring14
  • Farm buildings and private storage buildings are exempt from the state building permit13
  • Ask the Department of Livestock whether the lot sits in open range or a herd district before you count on anyone else’s fence
5

Phase 5 · Every year after

Resilience

By now the place works. This phase is what keeps it working through a hard winter, a smoky August or a lean month.

  1. Finish the fire rings. Keep the first 5 ft around the house bare of anything that burns, keep 5 to 30 ft lean and green, and thin the timber out to 100 ft. Those are the three zones Montana DNRC names.30
  2. A second way to do each thing. Two ways to heat (wood and one other), two ways to pump water (solar and the generator), two ways to keep food (the cellar and jars).
  3. Wood two winters ahead. Cut this year what you will burn the year after next. Dry wood is the cheapest insurance on the place.
  4. Put the future ground to work. The 160 x 102 ft along the road becomes a fifth paddock, a hay patch or a cabin for family, when you are ready and not before.
  5. Write the household plan. A homestead plan covers the land. A household plan covers the first hour of a bad day: who calls whom, where you meet, what you grab. Ready or Not Co. writes those too.

Hire out

  • A forester for one walk through the woodlot, if the timber is thick

Do it yourselves

  • Everything else. This phase is habit more than construction

Permits and filings

  • A burn permit, activated each day you burn; “having a permit is not the same as being approved to burn today”22
  • Check the county air quality line, 1-866-207-2577, before lighting23

Everything you need to build it

Materials and tools, sized to this drawing

Every length and volume below was measured from sheet S-1. Change the drawing and the list changes with it.

121cubic yards of gravel
1,368feet of woven wire
636feet of deer fence
337feet of water line
16solar panels
12fruit trees

1 Access, water and a place to stay

WhatHow muchWhere the number comes from
Driveway and court gravel, base course at 4 in70 cu yd5,696 sq ft: 306 ft x 12 ft plus the 44 x 46 ft court
Driveway and court gravel, top course at 2 in35 cu ydSame area
Geotextile fabric under the base5,700 sq ftSame area, rounded up
Culvert at the road ditch1Length and diameter are set by the county permit
Gate, 14 ft, with two posts1At the approach
Well, pump, pressure tank1 setDepth unknown until drilled
Water line, well to house64 ftBuried below frost; your driller sets the depth
Frost-free yard hydrant1At the court; two more come later
ToolsChainsaw, pole saw, wheelbarrow, shovels, rake, 100 ft tape, marking paint, stakes

2 Septic, power and the house shell

WhatHow muchWhere the number comes from
Septic tank1Size set by the designer
Sewer line, house to tank27 ftMeasured on S-1
Line, tank to distribution box18 ftMeasured on S-1
Drainfield laterals, as drawn360 ftFour at 90 ft; the designer sets the final length
Solar panels, 400 watt16Two rows of eight on a 30 ft rack
Power shed8 x 10 ftBatteries, inverter, generator pad
Power trench, shed to house36 ftMeasured on S-1
Pump circuit, house to well64 ftRuns beside the water line
House foundation144 ft of perimeter28 x 44 ft footprint, 1,232 sq ft
Porch8 x 32 ftSouth side
ToolsFraming nailer, circular saw, miter saw, levels, ladders, scaffold, trenching shovel or rented trencher

3 Food: garden, orchard and hens

WhatHow muchWhere the number comes from
Deer fence, 8 ft, garden300 ft70 x 80 ft perimeter
Deer fence, 8 ft, orchard336 ft72 x 96 ft perimeter
Tall fence posts at 10 ft64636 ft of fence in all
Gates4Garden: one 4 ft, one 10 ft. Orchard: one 4 ft, one 10 ft
Bed lumber, 2 x 6 x 124812 beds, two boards high on each long side
Bed lumber, 2 x 6 x 824Cut in half for the 4 ft ends
Soil and compost mix for beds20 cu yd12 beds x 4 x 12 ft x 11 in deep
Hoop house12 x 24 ftKit or bent conduit
Fruit trees12Cold-hardy apple, pear, plum and tart cherry
Coop8 x 12 ft
Run fence156 ft36 x 42 ft perimeter, plus an electric wire or net outside it
Compost bins3 at 4 x 4 ft
Water line, well to garden and coop128 ftMeasured on S-1, with one hydrant
Rain tanks at the house2Ask DNRC before you rely on them; see the rules section
ToolsPost hole digger or rented auger, fence stretcher, broadfork, spade, hoes, cart, drip line and timer

4 Animals, storage and the root cellar

WhatHow muchWhere the number comes from
Woven wire fence, 48 in1,368 ft820 perimeter + 330 cross + 218 winter yard
Line posts at 12 ftabout 114Plus braced wood posts at every corner and end
Pasture gates, 12 ft5One for each paddock and one for the yard
Barn and shop30 x 40 ft1,200 sq ft
Gravel for the barn spur11 cu yd base, 5 cu yd top71 ft x 12 ft
Water line, well to court and barn145 ftMeasured on S-1, with two hydrants
Power trench, house to barn122 ftMeasured on S-1
Root cellar12 x 16 ft192 sq ft, bermed
Woodshed8 x 16 ftOpen front, metal roof
Rain tank at the barn1Same question for DNRC
ToolsFence stretcher, T-post driver, come-along, auger, tamping bar

5 Resilience

WhatHow muchWhere the number comes from
Fence for the future ground, if grazed524 ft160 x 102 ft perimeter
Firewood racks or a second woodshed bay1
Backup generator and stored fuel1On the pad at the power shed
Pantry and cellar shelvingTo fit192 sq ft of cellar
ToolsSplitting maul or splitter, pressure canner, seed-saving jars, a printed binder of every manual on the place

What it costs

Wide ranges, honestly labelled

Every figure here is an estimate that varies by county and contractor. Each one names where it came from. Where we could not verify a number, we say so and tell you to get a quote.

ItemPublished rangeBasis
Well, drilled$25 to $65 per foot. $10,000 to $20,000 for a typical Flathead Valley well of 100 to 300 ftPublished 2026 Montana figures from a real estate guide, not a driller’s bid.33 Depth is the unknown.
Well pump and pressure tank$1,200 to $3,500 for the pump, $400 to $1,200 for the tankSame Montana guide.33
State well filings$400 Notice of Intent, then $250 Notice of CompletionDNRC’s own fee schedule and handout.8 9
Septic system$10,000 to $18,000 for conventional gravity, $14,000 to $22,000 for pressure distribution, $18,000 to $30,000 for a moundPublished 2026 Montana figures.33 Which type you are allowed is the county’s call after it sees your soil.
Septic permit and review$300 to $475 for the permit, $275 for a site evaluation or $150 for a site reviewCounty schedule dated April 22, 2021, still the one the county links.4 Confirm at (406) 751-8130.
Driveway and court$1 to $3 per square foot. On this drawing’s 5,696 sq ft that works out to about $5,700 to $17,100National 2026 range for gravel driveways.34 Rural base work in Montana can run past it.
Culvert at the approachGet a local quoteWe found no published figure we would put our name beside.
Off-grid solar with batteries$30,000 to $70,000 for a whole-house alternating current system; small direct current cabin systems $6,000 to $10,000National figures.35 Where a 6.4 kilowatt system lands depends mostly on the battery bank. Get two installer bids.
Utility power insteadGet a work order estimateFlathead Electric gives no per-foot figures.36 One national guide puts line extensions at $6.50 to $30 per foot.37 With no power at the lot line, the distance is the whole question.
House shellGet a local quotePublished per-square-foot figures for Montana disagree too widely to print. Price it from a lumber takeoff and two builder bids.
Barn and shop, 30 x 40 ft$35 to $50 per square foot built, which is $42,000 to $60,000. Kits $12,000 to $25,000A Midwest post-frame builder’s published 2026 range.38 Montana snow loads and freight can add to it.
Rain tanks, 1,500 gallon class$1,700 to $2,700 each before shippingRetailer list prices.39
Fencing, trees, coop, beds, hoop houseGet a local quotePrice the quantities in the lists above at a farm supply and a nursery near you. We could not verify current printed prices.

Permits and rules

What Flathead County and Montana require

Checked against official sources in November 2026 and cited below. Rules change. Where we could not verify something, it is listed as a question to ask, not stated as a fact.

Septic

Flathead City-County Health Department, Environmental Health, (406) 751-8130

  • A permit comes first. It is unlawful to build, alter or repair a system without a county installer license, and the county offers a homeowner self-installer license.1 3
  • Start with a Land Research Request. The county says: “Do not submit a septic permit application until you have completed a Land Research Request and received our response.”2
  • Where the lot has no Certificate of Subdivision Approval, “a site evaluation must be conducted by the Department.” The Department may ask for a test hole.1
  • If groundwater is within 7 feet of the surface, monitoring holes go in to at least 8 feet.1
  • Minimum distances in the county table: drainfield 100 ft from a well and from surface water, tank 50 ft from each, and 10 ft from foundations and property lines for both.1
  • Room for a full replacement field is required.1
  • State sanitation review attaches to land divisions that create parcels under 20 acres.6 For a lot that already exists, the question to ask is whether it has its certificate and what that certificate approved.

Ask the county or the state

  • Does this lot have a Certificate of Subdivision Approval, and for what kind of system?
  • Will my soil take a gravity system, or does the county require pressure dosing here?
  • Is the fee schedule dated 2021 still current?

Well and water right

Montana DNRC, Kalispell regional office; Montana Board of Water Well Contractors

  • A small domestic well can be developed without a water use permit if it is “35 gallons a minute or less, and does not exceed 10 acre-feet a year,” outside a stream depletion zone.10
  • New in 2026: “water users who intend to develop water use through a permit exception must file a Notice of Intent with DNRC before using water from an exempt well.” The form fee is $400.8
  • After that, a Notice of Completion (Form 602, $250) is what produces the water right. The statute sets it “within 60 days of completion of the well.”10 9
  • Drilling takes a licensed water well contractor, with a narrow exemption for owners who get a permit from the Board.11

Ask the county or the state

  • Is this lot inside any stream depletion zone or controlled groundwater area?
  • Does the Flathead water compact change anything for this lot?
  • May I collect roof rain in tanks for the garden without a water right? We could not find an official Montana statement either way, so the tanks on S-1 wait on this answer.

Building, electrical and plumbing

Montana Department of Labor and Industry; Flathead County Planning and Zoning, (406) 751-8200

  • The county does not issue building permits: “Flathead County does not have a building department and our office does not regulate the uniform building codes.”12
  • The state exempts “private homes and apartments with four or fewer units that do not serve transient guests,” farm or ranch buildings, and private garages or storage buildings.13
  • “An electrical permit is required for any installation in any new construction, remodeling or repair.” A homeowner may wire their own home under a homeowner permit, and the work is inspected.14
  • Homeowners “do not need to obtain a plumbing permit” when they do the plumbing themselves on a residence “for the owner’s personal use.”15

Ask the county or the state

  • Is this lot in a zoned district, and which one?
  • Are there recorded covenants?
  • Does my solar and battery work fall under the homeowner permit or the alternate energy permit?

Driveway, address and the creek

Flathead County Road and Bridge, (406) 758-5790; County GIS, (406) 758-5540; Flathead Conservation District, (406) 752-4220

  • A county roadway permit covers an approach; it is “generally required when creating, changing, or improving access between private property and a county road.”16
  • “The GIS department handles new address assignment and road naming for unincorporated Flathead County.”17
  • Montana’s streambed law covers “any natural, perennial-flowing stream or river, its bed, and its immediate banks.”18 Whether a seasonal creek counts is the Conservation District’s decision, and there “is no cost to getting a permit.”19
  • New development inside a mapped special flood hazard area needs a floodplain development permit.20
  • In the county’s standard zoning districts, “a 20-foot setback is required from streams, rivers and unprotected lakes.”21

Ask the county or the state

  • What does the approach permit cost, and what culvert does it call for?
  • Does the Conservation District treat this creek as a stream under the 310 law?
  • Is any of the lot in the mapped floodplain?
  • If the lot is unzoned, is there any stream setback for buildings?

Burning and fire

Flathead City-County Health Department, Air Quality; the local fire district

  • Flathead County issues burn permits through the Montana Burn Permit and Notification Service. “You only need one burn permit per person.” “Activate your permit each day before burning.”22
  • “Do not burn garbage, treated or painted wood, plastics, tires, food waste, hazardous waste, or other man-made materials.”22
  • “To find out if open burning is allowed today, call 1-866-207-2577.”23
  • State law sets wildfire season as “the period of each year beginning May 1 and ending September 30” and requires an official written permit to ignite during it.24

Ask the county or the state

  • Which months is open burning closed here this year?
  • Which fire district covers the lot, and how far is the nearest engine?

Animals and fences

Montana Department of Livestock; Montana Fish, Wildlife and Parks

  • “Open range” in Montana means “all lands in the state of Montana not enclosed by a fence of not less than two wires in good repair.”27
  • FWP’s guidance for bear country: electric fence around chickens, goats and sheep; “store livestock feed in a secure building”; and “consider installing an electric fence around fruit trees and gardens.”28

Ask the county or the state

  • Is the lot in open range or a herd district?
  • If zoned, how many animals does the district allow on five acres?

The first year

A calendar for this climate

May 31median last spring freeze
September 10median first fall freeze
100 daysmedian season between them
16.76 inprecipitation in a normal year
54.4 insnowfall in a normal year

NOAA 1991 to 2020 climate normals for the Kalispell airport station, at the 32 degree threshold.25 The airport is a cold spot: the Montana State University research center at Creston, east of Kalispell, records a median last frost of May 19, a first frost of September 16 and a 122 day season.26 Your own slope will sit somewhere near these. Keep a notebook and trust it over both.

December to February

Winter

  • Paperwork season. File the Land Research Request and ask about groundwater monitoring, which can begin as early as January 1.
  • File the DNRC Notice of Intent for the well.
  • Order bare-root fruit trees and seed for spring.
  • Walk the lot in snow. Mark where it drifts and where the low sun reaches.
  • Line up a driller, an excavator and a septic installer before their spring fills.

March to May

Spring

  • Groundwater readings continue through the wet months.
  • Approach permit, then culvert and driveway once the ground firms.
  • Fence the orchard and plant the trees as soon as the soil can be worked.
  • Drill the well. Set the first hydrant.
  • Start thinning the timber edge before fire season opens on May 1.
  • Sow peas, spinach and onions under cover. Half of all years still freeze after May 31.

June to August

Summer

  • Set out tomatoes, squash and beans in early June with covers ready. One year in ten brings a freeze after June 22.
  • Septic install and inspection.
  • Foundation and framing. Aim to have the roof on by the end of August.
  • Build the garden fence and the first six beds.
  • Keep the 5 ft ring around the trailer and the build site bare. This is fire season.
  • Rest one day in seven. The land will still be there on Monday.

September to November

Fall

  • Expect the first frost around September 10. One year in ten it comes before August 26.
  • Windows and doors in. Close the shell before snow.
  • Plant garlic. Mulch the orchard and wrap young trunks.
  • Stack two winters of wood under cover.
  • Drain and check every hydrant. Mark the driveway edges for the plow.
  • Sit down with the year. Write what the land taught you before you plan the next one.

Plain words

What this plan is, and what it is not

This is a site plan and a build sequence to plan with. It shows where things can go, in what order to build them and what they take.

It is not a set of stamped construction drawings, it is not engineering and it is not a survey. The septic system is designed and permitted through the county. The well is sited by your driller. Property corners are found by a licensed surveyor. Costs are published ranges, not bids.

Being ready is good stewardship of a family and a home. A plan on paper is where that starts.

Sources

Where every rule and number came from

  1. Flathead City-County Health Department, Regulations for Onsite Wastewater Treatment Systems, revised April 1, 2026 (sections 4.6, 5.1, 7.1, 10.2 Table 1, 10.3). flatheadcounty.gov/download_file/view/0ee5ba59-a8ce-4897-9a6f-a2fde2b00f30/675
  2. Flathead City-County Health Department, Septic Permit Application page. flatheadcounty.gov/department-directory/health/environmental-health/sewage-and-septic/septic-permit-application
  3. Flathead City-County Health Department, Licensed Installers and Self-Installers. flatheadcounty.gov/department-directory/health/environmental-health/sewage-and-septic/licensed-installers-and-self-installers
  4. Flathead City-County Health Department, Wastewater Fees, effective April 22, 2021 (the schedule the county links today). flatheadcounty.gov/application/files/3416/5790/5670/SepticFeeSchedule-4.22.21.pdf
  5. Flathead City-County Health Department, Groundwater Monitoring application, updated December 22, 2025. flatheadcounty.gov/application/files/5717/6782/1759/2025_GWM_Application_12-22-25.pdf
  6. Montana Code Annotated 76-4-102, Sanitation in Subdivisions, definitions. mca.legmt.gov/bills/mca/title_0760/chapter_0040/part_0010/section_0020/0760-0040-0010-0020.html
  7. Montana DNRC, Water Rights Permit Exceptions. dnrc.mt.gov/Water-Resources/Water-Rights/Apply-for-Water-Rights/Water-Rights-Permit-Exceptions
  8. Montana DNRC, Notice of Intent handout (Form 602I, in effect January 1, 2026). dnrc.mt.gov/_docs/water/Notice-of-Intent-Handout.pdf
  9. Montana DNRC, Form 613 fee schedule, revised January 2026. dnrc.mt.gov/_docs/water/Water-Rights-Forms/613.pdf
  10. Montana Code Annotated 85-2-306, exceptions to the permit requirement. mca.legmt.gov/bills/mca/title_0850/chapter_0020/part_0030/section_0060/0850-0020-0030-0060.html
  11. Montana Code Annotated 37-43-302, water well contractor license. mca.legmt.gov/bills/mca/title_0370/chapter_0430/part_0030/section_0020/0370-0430-0030-0020.html
  12. Flathead County Planning and Zoning, Building Information. flatheadcounty.gov/department-directory/planning-zoning/building-information
  13. Montana Department of Labor and Industry, Building Permit FAQ. bsd.dli.mt.gov/Building-Codes-Permits/permit-applications/building-permits/building-permit-faq
  14. Montana Department of Labor and Industry, Electrical Permits. bsd.dli.mt.gov/Building-Codes-Permits/permit-applications/electrical-permits
  15. Montana Department of Labor and Industry, Plumbing Permits. bsd.dli.mt.gov/building-codes-permits/permit-applications/plumbing-permits
  16. Flathead County Road and Bridge, County Roadway Permit Applications. flatheadcounty.gov/department-directory/roads-and-bridges/county-roadway-permit-applications
  17. Flathead County GIS, address assignment. flatheadcounty.gov/department-directory/gis
  18. Montana Code Annotated 75-7-103, Natural Streambed and Land Preservation Act, definitions. mca.legmt.gov/bills/mca/title_0750/chapter_0070/part_0010/section_0030/0750-0070-0010-0030.html
  19. Flathead Conservation District, What Is a 310 Stream Permit. flatheadcd.org/what-is-a-310-stream-permit
  20. Montana DNRC, Stream Permitting. dnrc.mt.gov/Licenses-and-Permits/Stream-Permitting
  21. Flathead County Zoning Regulations, May 2026. flatheadcounty.gov/application/files/3617/7947/4647/FCZR_May_2026.pdf
  22. Flathead City-County Health Department, Burn Permit. flatheadcounty.gov/department-directory/health/environmental-health/burn-permit
  23. Flathead City-County Health Department, Air Quality and Ventilation. flatheadcounty.gov/department-directory/health/environmental-health/air-quality-and-ventilation
  24. Montana Code Annotated 76-13-102 and 76-13-121, wildfire season and permits. mca.legmt.gov/bills/mca/title_0760/chapter_0130/part_0010/section_0020/0760-0130-0010-0020.html
  25. NOAA National Centers for Environmental Information, 1991 to 2020 U.S. Climate Normals, station Kalispell Glacier AP (USC00244558). ncei.noaa.gov/data/normals-annualseasonal/1991-2020/access/USC00244558.csv
  26. Montana State University, Northwestern Agricultural Research Center (Creston), Summary of Climatic Data. sarc.montana.edu/oldMWBC/documents/mwbc/2018/5%20SummaryOfClimaticData.html
  27. Montana Code Annotated 81-4-101 (legal fences) and 81-4-203 (open range). mca.legmt.gov/bills/mca/title_0810/chapter_0040/part_0010/section_0010/0810-0040-0010-0010.html
  28. Montana Fish, Wildlife and Parks, Living in Bear Country. fwp.mt.gov/conservation/wildlife-management/bear/be-bear-aware/living-bear-country
  29. Montana Code Annotated 69-4-502 and 69-4-503, excavation near underground facilities. mca.legmt.gov/bills/mca/title_0690/chapter_0040/part_0050/section_0030/0690-0040-0050-0030.html
  30. Montana DNRC, Fire Prevention and Preparedness (home ignition zone). dnrc.mt.gov/Forestry/Wildfire/fire-prevention-and-preparedness
  31. Western Regional Climate Center, Prevailing Wind Direction table, Kalispell AP, hourly data 1992 to 2002. wrcc-archive.dri.edu/Climate/comp_table_show.php?stype=wind_dir_avg
  32. Montana Bureau of Mines and Geology, Ground Water Investigation Program, Flathead Valley Deep Aquifer. mbmg.mtech.edu/gwip/projects/project_flathead.html
  33. AskDoss, How Much Does a Well Water System Cost in Montana in 2026 (published February 24, 2026, updated March 8, 2026). A real estate guide, not a driller.. askdoss.com/how-much-does-a-well-water-system-cost-in-montana-in-2026
  34. LawnStarter, Gravel Driveway Price (updated October 5, 2026), national figures. lawnstarter.com/blog/cost/gravel-driveway-price
  35. This Old House, Off-Grid Solar System Cost (updated June 11, 2025), national figures. thisoldhouse.com/solar-alternative-energy/reviews/off-grid-solar-system-cost
  36. Flathead Electric Cooperative, Residential Handbook, How to Start a Work Order. flatheadelectric.com/my-account-bill/new-construction/residential-handbook/how-to-start-a-work-order
  37. Utility Cost Guide, Cost to Run Power to Property in 2026 (reviewed November 9, 2026), national figures. utilitycostguide.com/cost-to-run-power-to-property
  38. FBi Buildings, 30 x 40 Pole Barn Costs (published January 12, 2026). A Midwest builder.. info.fbibuildings.com/blog/30-x-40-pole-barn-costs-diy-kits-vs.-construction
  39. National Tank Outlet, Norwesco vertical storage tanks, list prices before shipping. ntotank.com/norwesco-vertical-storage-tanks

Sample Homestead Plan no. 01. A made-up property, drawn to show the product.

Get a plan for your landOpen the PDF